摘要:介绍百事亚洲研发中心,采用智能电力仪表、采集配电现场的各种电参量和开关信号。系统采用现场就地组网的方式,组网后通过现场总线通讯并远传至后台,通过Acrel-2000型电力监控系统实现配电所配电回路用电的实时监控和管理。

关键词:配电所;智能电力仪表;电力监控系统;

AbstractIntroduce the Pepsi Asia R&D Center, which uses smart power meters to collect various electrical parameters and switch signals at the distribution site. The system adopts the method of on-site networking. After networking, it communicates through field bus and transmits it to the background. The Acrel-2000 power monitoring system realizes real-time monitoring and management of power in distribution stations.

Keywords:Distribution stations;Intelligent power meter;Power monitoring system

1 概述 Project Overview

百事亚洲研发中心位于漕河泾开发区浦江高科技园。该研发中心是百事公司在北美之外的研发中心,也是百事公司在全球具整合性的食品和饮料研发中心之一,在百事公司全球研发网络中发挥举足轻重的作用。

百事亚洲研发中心占地约25亩,建筑面积近2万平方米,中心还设有一个测试生产工厂,使研发者得以快速测试新产品,支持百事公司加速在中国和其它成长中亚洲市场进行研发创新。

本次项目承接其的变配电所部分监控系统。

Pepsi Asia R&D Center is located in Pujiang High-Tech Park, Caohejing Development Zone. The R&D center is PepsiCo’s largest top R&D center outside North America and one of PepsiCo’s most integrated food and beverage R&D centers in the world. It plays a pivotal role in PepsiCo’s global R&D network. 

The Pepsi R&D Center in Asia covers an area of about 25 acres and has a building area of nearly 20,000 square meters. The center also has a test production plant that allows developers to quickly test new products and supports PepsiCo to accelerate R&D in China and other growing Asian markets Innovation.

This project undertakes part of the monitoring system of its substation and distribution station.

2 系统方案

安科瑞电力监控系统根据百事亚洲研发中心现场实际情况,整体网络结构采用屏蔽双绞线直接接至配电所的数据采集器然后直接接至开闭所的监控主机,保障了配电所电力监控系统传输的稳定性与实时性。

According to the actual situation of Pepsi Asia R&D Center, Acrel power monitoring system adopts shielded twisted pair cable to connect directly to the data collector of the power distribution station. Then it is directly connected to the monitoring host of the switching station to ensure the stability and real-time transmission of the power monitoring system of the distribution station.